EtherCAT and commissioning
Configure and verify the EtherCAT system before commissioning motion.
Commissioning order
- Supported slaves — select hardware and find its configuration files.
- Advanced EtherCAT and commissioning — configure domains, data items, DC, verification, and topology handling.
- EtherCAT endpoint timing — configure delays, phase, timestamps, and diagnostic PVs.
- Verify DC timing with position compare — check timed outputs against a touch probe.
Test without physical EtherCAT
Simulation backend (SIM=1)
uses typed memory with the normal signal names. Separate Python models provide
drive feedback; generated SIM PVs support manual injection and a live GUI.
Additional configuration
For communication faults, use the EtherCAT command line guide and hardware notes.